Experience
AirTek is a leading provider of engineering, construction,
and maintenance services for air pollution control (APC)
equipment in a wide range of industries including power
generation, pulp and paper, petrochemical, rock products,
and steel. We specialize in providing turnkey solutions
for precipitator design, engineering, erection, and
maintenance.
Following is a brief summary of some of our projects:
Smurfit Corporation Florence, SC
- New precipitator with inlet duct work, slide gates, and prefabricated control room on a combination fuel power boiler.
- Turnkey scope included engineering, material, erection, low voltage wiring, insulation, and lagging.
Smurfit Corporation Brewton, AL
- New precipitator with inlet slide gates, outlet stacks, and ash handling system on a combination fuel power boiler.
- Turnkey scope included engineering, material, erection, low voltage wiring, insulation, and lagging.
Weyerhaeuser Company Campti, LA
- New precipitator with support steel and material removal system on a recovery boiler.
- Scope included engineering and material supply.
Georgia Pacific Corporation Palatka, FL
- Rebuild one oil fired and one combination fuel fired boiler precipitator.
- Fill empty field including electric impulse rappers and a transformer rectifier on oil fired unit.
- Supply collecting plates and rigid electrodes on combination fired unit.
Weyerhaeuser Company Valliant, OK
- Lime kiln precipitator installation and supply of foundations, support steel, ductwork, black liquor system, and new electrical substation.
- Turnkey scope included precipitator erection, low voltage electrical work, piping, and project management.
Weyerhaeuser Company Valliant, OK
- Recovery boiler precipitator installation and supply of foundations, support steel, ductwork, black liquor system, and electrical substation.
- Turnkey scope included precipitator erection, all low voltage electrical work, piping, project management, and demolition of existing precipitator.
Weyerhaeuser Company Pine Hill, AL
- Rebuild a recovery boiler precipitator. Scope included engineering and replacement of inlet ductwork.
- Turnkey scope included engineering, material, erection, low voltage wiring, insulation, and lagging.
Smurfit-Stone Corporation Hopewell, VA
- Rebuild of the combination fuel fired boiler precipitator.
- Convert to rigid electrodes, supply collecting plates, rappers, transformer rectifier sets and controls, and major plenum repairs.
- Turnkey scope included engineering, material, erection, low voltage wiring, insulation and lagging.
|
|